Road Upgrading Process: Excavation, Sub-base, Drainage and Bitumen Works

A stage-by-stage road upgrading guide covering excavation, formation, drainage, sub-grade, sub-base, compaction, bitumen works, measurement, and quality control.

Premix paving work at Jaldhare

Road upgrading is a sequence of dependent layers and drainage works. Covering a weak layer with the next item usually transfers the defect into the finished pavement.

Published by: Jwala Nirman Sewa

Practical context: construction execution, measurement, BOQ and infrastructure-work experience in Nepal.

Formation to sub-base

Set out the alignment, complete approved excavation and protection, form drainage, remove soft spots, control moisture, and compact each layer to the required width, thickness, level, and density.

Bituminous and finishing works

The receiving surface must be clean, dry, shaped, and approved. Prime/tack application, mix temperature, spreading, rolling pattern, joints, edges, and final surface tolerance require documented control.

People carrying out a pavement site check at Jaldhare
A closer view of the related site activity.

Note: Actual work should follow the signed contract, approved drawings, BOQ, specifications, authorized engineer’s instructions, and applicable public-procurement and safety requirements.

Frequently Asked Questions

Can drainage be completed after pavement?

Some finishing may follow, but primary drainage should generally be functional before pavement layers are exposed to runoff.

Why is layer-wise approval needed?

Later layers hide earlier work. Inspection and measurement before covering protect quality and billing accuracy.

Related Resources

Related Resources

Road & Infrastructure

Road Construction in Pokhara and Gandaki Province

Practical guidance on road construction in Pokhara and Gandaki: survey, excavation, drainage, sub-base, bitumen, QA/QC, and hill-terrain planning.

Read guide
Gabion / Retaining / Slope Protection

Gabion Wall and Stone Masonry Works in Nepal

How gabion and stone masonry works are planned, constructed, measured, and quality-checked for roads, slopes, drains, and river protection in Nepal.

Read guide
Road & Infrastructure

Irrigation Canal Upgradation Works in Nepal

Planning and execution of canal upgradation in Nepal, including flow diversion, excavation, lining, structural repair, outlets, measurement, and QA/QC.

Read guide
Road & Infrastructure

Landslide Clearance and Hill Road Protection Works in Nepal

Safe planning for landslide clearance, roadway excavation, spoil management, drainage, gabion, masonry, and slope protection on Nepal hill roads.

Read guide
Construction Materials & Prices

How Contractors Manage Price Rise in Bitumen, Fuel and Construction Materials

How contractors plan procurement, records, cash flow, rate exposure, and contract compliance when bitumen, fuel, cement, steel, and aggregates rise in price.

Read guide
BOQ / Billing / Contracts

BOQ, Measurement and Final Bill Process in Nepal Construction Contracts

A practical overview of BOQ items, joint measurement, running bills, variations, as-built records, reconciliation, and final bill preparation in Nepal.

Read guide