Road Construction in Pokhara and Gandaki Province
Practical guidance on road construction in Pokhara and Gandaki: survey, excavation, drainage, sub-base, bitumen, QA/QC, and hill-terrain planning.

Road work in Gandaki must account for steep terrain, monsoon water, variable soil, settlement access, and material haul distance. A workable construction plan starts with survey control and drainage—not surfacing.
Published by: Jwala Nirman Sewa
Practical context: construction execution, measurement, BOQ and infrastructure-work experience in Nepal.
Typical execution sequence
The approved drawing, BOQ, chainage, formation width, levels, and disposal locations should be confirmed before bulk excavation.
Practical checklist
- Survey and setting out
- Excavation and road formation
- Side drains, cross-drainage, and protection works
- Sub-grade preparation, sub-base and base compaction
- Prime/tack coat, premix or specified bituminous layer, and finishing
Quality and measurement controls
Layer thickness, moisture, compaction, line and level, drain dimensions, masonry workmanship, and bitumen temperature/application must follow the specification and engineer’s direction. Running bills should be supported by joint measurement and site records.

Note: Actual work should follow the signed contract, approved drawings, BOQ, specifications, authorized engineer’s instructions, and applicable public-procurement and safety requirements.
Frequently Asked Questions
What usually causes road failure in hill areas?
Uncontrolled water, weak compaction, unsuitable fill, inadequate slope protection, and delayed maintenance are common causes.
Should bitumen work continue during rain?
Generally no. The surface and weather conditions must satisfy the project specification and supervising engineer.
Related Resources
Related Resources
Gabion Wall and Stone Masonry Works in Nepal
How gabion and stone masonry works are planned, constructed, measured, and quality-checked for roads, slopes, drains, and river protection in Nepal.
Read guideIrrigation Canal Upgradation Works in Nepal
Planning and execution of canal upgradation in Nepal, including flow diversion, excavation, lining, structural repair, outlets, measurement, and QA/QC.
Read guideRoad Upgrading Process: Excavation, Sub-base, Drainage and Bitumen Works
A stage-by-stage road upgrading guide covering excavation, formation, drainage, sub-grade, sub-base, compaction, bitumen works, measurement, and quality control.
Read guideLandslide Clearance and Hill Road Protection Works in Nepal
Safe planning for landslide clearance, roadway excavation, spoil management, drainage, gabion, masonry, and slope protection on Nepal hill roads.
Read guideHow Contractors Manage Price Rise in Bitumen, Fuel and Construction Materials
How contractors plan procurement, records, cash flow, rate exposure, and contract compliance when bitumen, fuel, cement, steel, and aggregates rise in price.
Read guideBOQ, Measurement and Final Bill Process in Nepal Construction Contracts
A practical overview of BOQ items, joint measurement, running bills, variations, as-built records, reconciliation, and final bill preparation in Nepal.
Read guide