Upgrading of Road from 3 No. Barrack Gate to Soto Chowk and Milijuli Marga Upallo Kadeni, PMC-26

Project at a Glance

Status
Ongoing
Our Role
Main Contractor
Contract ID
37/PMC/NCB/W/Purbadhar/082-83
Client / Employer
Pokhara Metropolitan City Office
Location
Pokhara-26, Kaski

Project Overview

Road upgrading including pavement preparation, drainage and side structures, bitumen-related works, and finishing to municipal specifications.

Our Role

Main Contractor

Jwala Nirman Sewa’s role is Main Contractor, executing construction within the approved contract scope, BOQ, drawings, specifications, and instructions of the responsible authority.

Scope of Work

  • Pavement and formation preparation
  • Drainage and side structures
  • Bitumen-related road works
  • Finishing to municipal specification

Execution Approach

Layer preparation, drainage completion, material control, compaction, bitumen-related activities, and finishing are sequenced through inspection and specification hold points.

Site Photography

Project Gallery

Real site photographs showing execution, preparation, equipment, and completed work.

Open concrete drain beside the access track at Soto Chowk
Open concrete drain beside the access track at Soto Chowk
Road formation and subgrade preparation at Soto Chowk
Road formation and subgrade preparation at Soto Chowk
Soiling and road construction materials at Soto Chowk
Soiling and road construction materials at Soto Chowk
Stone soiling before PCC and plum work on Soto Chowk Marga
Stone soiling before PCC and plum work on Soto Chowk Marga

Related Projects

Related Projects

Other current and completed infrastructure works in similar disciplines.

Need similar work?

Share your location and scope to start a project discussion.

Discuss a Project